And Diospi Suyana is always building
A subcontractor is welding on the roof construction above the conference hall. The leisure center should be covered by the end of October. The plastering work on the building is continuing. It would be great if the project could be completed by the third youth festival.
Behind the hospital, some men are working on the details of the third storage room (60 m2). We also hope to transport the incinerator from the carpentry workshop to its new home. This project will probably be completed in November.
What we don’t manage to do by April 2025 will have to go into a holding pattern, because immediately after the next festival our full concentration will be on the school buildings.