The construction of the leisure center is moving upwards

The progress of the last week

Dear Diospi Suyana friends, I am happy and grateful that on Tuesday and Wednesday we were able to pour the first construction phase of the upper floor slab including the continuous balconies on both sides. Around 40m³ of concrete was mixed on the ground in the old familiar manner, hoisted upwards using an old-fashioned winch with a petrol engine and moved and installed on the ceiling using wheelbarrows. However, the winch held up well and ran smoothly on both days.

Shuttering the balcony on the valley side was time-consuming and not entirely safe due to its height. As already reported, the construction of an intermediate platform was necessary.

On the first floor, plastering continued this week, depending on available manpower, and the brackets for the rising columns were bent.

Best wishes from Curahuasi and have a blessed weekend! Udo

The-supporting-construction-stands-on-a-temporary-intermediate-pedestal.
The supporting structure stands on a temporary intermediate platform.
Things are moving forward, but safety first.
The pull-off points for concrete installation are leveled.
The concrete winch is ready for use.
And another bucket is emptied.
Let’s go to the installation site.
The mixing crew in action
The first day’s destination is soon reached.
The work is done.