1 Stuetzenkoepfe im 3

Exactly documented by constructional engineer Udo Klemenz

Dear friends of Diospi Suyana, this week the Colegio Diospi Suyana was on break. Most missionaries with school aged children use the days off school for a short vacation trip. That has had an impact on the hospitals services as well, so a few surgeries were cancelled and fewer patients were on the wards. We construction people used the opportunity to do the noise intensive work of chiseling down the pillars on the concrete ceiling over the ward (2. phase of the construction).

The brick work in the first phase are coming to an end slowly. The supporting walls are nearly ready. The non-supporting walls in the bathrooms of the two-bed rooms have a lot of corners and take a little longer accordingly.
The window and door lintels are all poured in place and right now shorings are being encased and poured-in-place. Two people are preparing the panels for the encasing of the ceiling.

In a part of the back garden we leveled and compressed the top soil and poured a thin layer of concrete. Here we will store the materials, that we need to make the concrete for the ceiling. In this part of the garden we will set up the elevator for the concrete as well.
The brick work of phase two has already started as well.

Sending greetings from Curahuasi and wishing you a nice and blessed weekend. Udo

2 Die Anschlusseisen fuer die Stuetzen werden auf die einbetonierten Stahlplatten geschweisst
The irons for the pillars are being welded onto the cemented steel plates.
3 Blick auf den Seitenfluegel
View onto the side wing.
4 Ausschalen von Aussteifungsstuetzen
Stripping the formwork of the pillars

 

5 Der Lagerplatz fuer die Zuschlagstoffe wird vorbereitet
The storage place for the materials is being prepared.

 

6 Die Deckenschalung wird vorbereitet
Preparation of the formwork for the ceiling

 

7 Transportwagen
Workshop chief Oebele de Haan is making a trolley out of an old bed.

 

Akkustikplatten fuer das Mediencenter
Detlev Hofmann is working on the sound absorbing panels for the media center.