The buildings that are being worked on this week are marked in red. By March at the latest they should have roofs and windows. The buildings in question are workshop, laundry facility, housing for short-term staff members, kitchen, cafeteria and outpatient clinic (on the left).
We have already had 524 volunteers help us with the construction of the amphitheater. 25 church communities are involved. We are keeping a diary to track of the details.
The third photo features a beautiful view over parts of the outdoor theater and the shells of the buildings under construction. Indeed, the area detailed in photograph one is no longer recognizable.
Next week, Diospi Suyana will have paid 28% of the total costs to construction company Constructec. Diospi Suyana does not have any debt and, on principle, does never incur debts. We are thankful to all donors, who made this quick construction progress possible.