Inspections at the Construction Site

Currently, there are three trucks that, 33 times a day, drive soil to the proposed construction site. The soil is needed to build the plateau on which the hospital will be constructed.

This work is scheduled to be finished in two weeks. Unfortunately, equipment has to be repaired again and again.

Today, on Monday, Mr. Klemenz performed his first quality control at the construction site. Previously, he worked for the German company Holzman in Africa and Asia, now he is in South America for Diospi Suyana.

His voluntary contributions will be crucial to the project’s success. On the right hand of the picture, you can see the mayor of Curahuasi Señor Luna.